Stopping New Works in the UAE: Preventive Protection of Possession

Stopping New Works in the UAE: Preventive Protection of Possession

The new Civil Transactions Law provides a preventive possessory action aimed at stopping new works that threaten possession before the interference is completed. The action has its own legal conditions and time requirements.

Preserve evidence of actual possession, the start date and progress of the works, site photographs and relevant inspection reports. Identify the particular threatened interference rather than relying on a general fear of future damage.

This procedure should be distinguished from a claim deciding ownership or an application challenging an administrative decision. The condition of the works and the nature of the requested protection influence the appropriate procedure.

Federal Decree-Law No. 25 of 2025 entered into force on 1 June 2026. Check the dates, applicable special legislation and temporal rules for the particular case.

Official sources

Civil Transactions Law | Official explanation of the reforms

Related reading

Preparing for a legal consultation.

General legal information; an individual case requires review of its records and applicable law.

Ali Saeed Al Shamsi, Advocate and Legal Consultant — +971 50 346 6632 — Request a consultation on WhatsApp.

Need your documents reviewed?

Share the issue, its stage and the nearest deadline to define the consultation and documents needed.

Request a consultation on WhatsApp0503466632